From September 2017 to January 2018, we successfully finished QA in-process and final inspection services of steel structures for abeltconveyer used for iron ore movement in Shenyang.The customer was Mitsubishi Corporation of Japan.

From February 2018 to MAY 2018, we successfully supplied inspection services of steel structures for 1 X 1000 MW Minjung Coal Fired Power Plant Project of Tenaga Nasional Berhad in Malaysia. Services included inspection for the fabricating process, final quality inspection after machining, witness all testing, shot blast quality inspection, painting quality inspection, packing quality inspection and document review.